Retail · Multi-site rollout

Retail estate — 12-site network rollout

Standardised IT infrastructure across twelve refitted stores — AP cabling, CCTV backbone and switch-ready patching delivered to a single specification for a national rollout programme.

South West & Midlands Completed January 2025
Organised copper and fibre cable bundles in basket tray and trunking
12
Sites delivered
96
AP locations
14 weeks
Rollout window

The challenge

A national retailer was refitting twelve stores on a rolling programme across the South West and Midlands. Each site needed identical infrastructure — wireless AP cabling, CCTV backbone and a small comms cabinet — installed to one standard so their IT partner could deploy equipment without site-specific variations.

The main contractor required a cabling subcontractor who could hold a master template for containment, labelling and test thresholds across every location.

Programme & mobilisation

We delivered sites on a rolling four-week cycle over a 14-week rollout window:

  • Weeks 1–2 — Template sign-off: cabinet layout, AP locations, CCTV backbone routes, labelling convention
  • Weeks 3–12 — Three sites per month average — survey, install, test, handover pack per store
  • Weeks 13–14 — Snag closure and template update for any client IT feedback

Each site handover included the same PDF structure so the client’s IT partner could commission switches and APs without re-interpreting documentation.

Technical scope

  • Cat6A cabling to 96 wireless access point locations across twelve sites (8 APs per store average)
  • Dedicated CCTV backbone links from each sales floor to the local comms cabinet
  • 12no wall-mounted comms cabinets — racks, patching and labelling to master template
  • Switch mounting rails and structured cable dressing ready for the client’s IT partner
  • Fluke certification on every copper link — same pass thresholds at every site

Standards & handover

Per-site handover packs included:

  • Outlet and AP location schedule (aligned to client floor plan grid)
  • Cabinet elevation and patch schedule
  • Fluke certification PDFs per outlet ID
  • Photos of cabinet dressing for QA records

Outcome

All twelve sites handed over within the 14-week rollout window. The client’s IT partner reported zero cabling-related delays during equipment commissioning.

Representative of our IT infrastructure and data cabling work across the West Midlands and South West.


Client identity withheld under NDA. Sector, scale and outcomes are representative of work delivered. References available on request.